| Client | CH2MHILL |
| Facility | KE Reactor |
| Location | Richland,WA |
S.A.Technology is contracted to perform the design, fabrication, installation, and related construction activities that will allow the K East (105-KE) reactor core to be demolished. The 105-KE Reactor Core Disposal Project will remove and dispose of the reactor core by size reduction and compliant packaging in approved waste containers for disposal at the Hanford Department of Energy (DOE) Environmental Restoration Disposal Facility (ERDF).The end point of the project is that the core (including thermal shield) will be removed to the point that standard demolition techniques can take place for the balance of the reactor building.
Demolition Operations
S.A.Technology Project Scope:
Phase 1 - Specialized Tooling and Site Preparation
- Finalize project plan
- Regulatory approvals
- Crane capacities
- Analyze natural phenomena
- Site preparation activities
Phase 2 - Reactor Core Removal
- Cut access in bioshield
- Remove graphite
- Remove thermal shield
- Waste Packaging
Phase 3 - Demolition of Balance of Plant
- Demolish concrete walls to 3' below grade
- Conventional demolition of exterior walls while applying fixative and dust suppression
- Backfill site